Inspection-Report_TFSAFE_Full_7NX32_Hangar-RM-1-CDP_128_18-06-26_1
QC RejectedReport Details
- TAG-ID
- TFSAFE_7NX32_Hangar-RM-1-CDP_128_18-06-26
- Work Order
- TFS-7NX32-2026-00007
- Site
- H-5 (Jordan) (7NX32)
- Building
- Hangar-RM-1-CDP
- Building Type
- HANGAR
- System Voltage
- 230/400
- Code Standard
- British Standard
Inspection Info
- Phase
- Full Inspection
- Date
- 18-JUN-2026
- Team
- 128
- Overall Rating
- Fair
- Location
- Hangar is located adjacent to the flightline. Rm-1 FSR office is located on right side of building as entered from the car park on the west wall.
Summary of Findings
No LHS found at time of inspection, Room 1 CDP inspected.
Building Picture
Update Report
Deficiencies (1)
Location: RCD within the CDP.
Category: Improper Terminations
Equipment: CDP
Occurrences: 1
Imminent Danger: No
Code Source: British Standard
Code Reference: 526: Electrical connections
Action Taken: N/A
SOR Issued To: O&M Provider
Description: Live and neutral have not been terminated in the correct terminals of the RCD as per manufactured instructions.
Signatures & QC
Comments: Good afternoon gents, Please see items below which require attention: 1. Building location – change comma at end of description to a full stop 2. Def 2 – description refers to the summary page but this report does not have a summary page: remove reference to summary or add a summary 3. Def 2 and 3 – these deficiencies were closed on a reinspection report in February: were they still present during this inspection, if not then they can be removed from this report If you have any questions, please give me a call
Please address the issues above and resubmit.
Status History
2
| Date | From | To | Changed By | Notes |
|---|---|---|---|---|
| 19-JUN-2026 | Pending QC | QC Rejected | Hugh Crawford | Good afternoon gents, Please see items below which require attention: 1. Building location – change comma at end of description to a full stop 2. Def 2 – description refers to the summary page but this report does not have a summary page: remove reference to summary or add a summary 3. Def 2 and 3 – these deficiencies were closed on a reinspection report in February: were they still present during this inspection, if not then they can be removed from this report If you have any questions, please give me a call |
| 18-JUN-2026 | Draft | Pending QC | Brett Smithson |